The status of work under the project Construction of the Nowy Teatr International Cultural Centre - May 1, 2015

Back

At the end of April 2015 we completed the strengthening of  the Vierendeel trusses. Works are still underway in removing the shattered plaster, insulating of the outer foundation walls, and in doorways, concrete floors and brick work. Roofing felt will be soon removed from the roof, and we are halfway through removing the cement and plaster from the facade. Some of the electrical wiring is already in place. We started plastering the facade and the interior. We also installed structures necessary in the modern theatre design.