The status of work under the project Construction of the Nowy Teatr International Cultural Centre - April 1, 2015

Back

In March 2015 reinforced concrete elements in the hall were completed, lean concrete was laid for new foundations, and steel brackets for beams were mounted.

Work is still underway in the insulation of the outer foundation walls and in strengthening the Vierendeel trusses. Concrete floors have been partially completed, and we're also half way through the masonry works. Tar from the roof of the hall is being removed, along with cement and plaster from the facade. First electrical installations have been carried out.

The final works are being carried out in the demolition of the administrative building, including the removal of ceramic tiles and installations.