The status of work under the project Construction of the Nowy Teatr International Cultural Centre - March 1, 2015

Back

By the end of February 2015 the demolition of walls and floors in the hall was completed, ground was prepared for new foundations, and new strip footings and pad foundations were laid.

The previous electrical and sanitary installations have been removed, hoop iron was used in the hall and under-floor sewerage was completed. Finals works are being performed in reinforced concrete structures (walls, pillars, ceilings and stairs). Works are still underway in mounting steel brackets for beams, removing the shattered plaster and in door openings. Insualtions works have started in the external foundation walls.

Final demolition works are being held in the administrative building.