Construction of Nowy Teatr ICC in October 2015

Back

In September 2015 we continued works in the workshop hall. Ceilings were completely renovated, suspended ceilings and acoustical ceiling tiles were installed; most of the acoustic panels were installed on the walls. Further installation works were performed, and most of the flooring was laid. Installation of the external steel windows continued. The facades of both buildings were plastered.

The roof of the administrative building was completely covered.

On 28 September 2015 a permit was granted for a change in the previous building permit, approving a replacement project taking into account extension of the reconstruction of the administration building.