In November 2015, works were continued in the historic workshop hall, in equipping the building with electricity, gas, water, ventilation systems, as well as theatre AV facilities. More floors were laid and interior doors were installed. We completed laying of the epoxy flooring in the bathrooms.

In the administration building, works continued in installing water, sewerage and electrical systems. Low voltage wiring was completed. Also approx. 30% of the brick laying and gypsum walls,  and approx. 40% of the internal plastering were completed.

60% of the sanitary installations were completed in the external area. The concierge building was demolished, the soil was stabilized and lean concrete was used to make a ground beam.