Construction of Nowy Teatr ICC in December 2015

Back

December 2015 saw the continued installation of AV, LAN and fibre-optic cables in the workshop hall. The reconstructed historic gates were installed. Dressing room bathrooms were fitted with showers and sinks.

In the administration building more walls were built, suspended ceilings were installed, as well as water, sewerage and electrical systems. Most concrete floors and some plaster on the walls and ceilings were laid. Construction of the reinforced concrete structures for the veranda and connector were started.

More sanitary installations were completed in the external area. Work was continued in soil stabilization and construction of the lean concrete ground beams.